Question: 1
Improving predictability is an important promise in Disciplined Agile. The best strategies to improve predictability is:

A. Provide adequate buffers
B. Limit the work-in-progress
C. Avoid risky work
D. Provide adequate resources

Answer: B
Explanation/Reference:
By limiting the work-in-progress, you can reduce the distractions, thereby improving predictability

Read More

[December-2021]Valid 2021-PMP PDF and VCE Dumps PDF Free Download in Braindump2go[Q725-Q755]

December/2021 Latest Braindump2go 2021-PMP Exam Dumps with PDF and VCE Free Updated Today! Following are some new 2021-PMP Real Exam Questions!

QUESTION 725
A newly appointed product owner is working with a project team that is using agile for the first time. The product owner is constantly disrupting various team members throughout the day to discuss progress. This has resulted in the team feeling micromanaged and frustrated because of the constant disruptions.
How should the project manager proceed?

A. Invite the product owner to attend daily standup meetings so they can assess progress.
B. Set up a feedback session with the product owner once a week so they can assess progress.
C. Instruct the team to refer the product owner to the project manager for information.
D. Invite the product owner’s functional manager to a feedback session to escalate the issue.

Answer: A

Read More

[July-2020]Exam Pass 100%!Braindump2go CAPM Exam VCE and PDF Dumps CAPM 1849Q Instant Download[1565-1586]

2020/July New Braindump2go CAPM Exam Dumps with PDF and VCE Free Updated Today! Following are some new CAPM Real Exam Questions!

QUESTION 1565
Which statement summarizes the role of the change control board?

A. The change control board is responsible for presenting the change for approval
B. The change control board will analyze the change impact in terms of cost and schedule
C. The change control board is responsible for managing the change management and configuration management systems
D. The change control board is responsible for reviewing and approving changes to the project